FERC Grants and Denies in Part Basin Electric’s Transmission Incentive Petition

On March 31, 2025, FERC granted in part and denied in part Basin Electric Power Cooperative’s (Basin Electric) petition for declaratory order seeking transmission incentives for the Roundup-Kummer Ridge Project, the Tande-Finstad-Leland Olds Project (LOS-Tande Project), and the NE Williston-Folvag 115 kV-Judson-East Fork-Tande Project (Springbrook Project) (collectively, “Projects”). FERC granted the Hypothetical Capital Structure Incentive and the Abandoned Plant Incentive to both the LOS-Tande...
By: Troutman Pepper Locke

Array